Thursday, September 10, 2009

Construction Updates from Holder

Here's the construction update from the week of September 4, 2009.

Current week - Activities/Issues:
New Gallery / Connector
• Installed roof joists.
• Installed roof decking.
• Installed skylight structural steel support.
• Poured concrete columns at the parking area.
• Poured retaining wall footings.
• Poured the R.5 Line Concrete Wall

Existing Building Renovations
• Investigating the existing MEP systems.
• Developing MEP demolition and reconfiguration plan

Storage Bar
• Continued to address and relocate existing site utilities including:
o Emergency Power
o Domestic Water


Next week - Activities/Issues:
New Gallery / Connector
• Build the limestone mock-up.
• Finish roof joists.
• Continue roof decking.
• Pour the balance of the concrete columns.
• Continue to pour retaining wall footings.
• Form and pour the signage wall.

Existing Building Renovations
• Continue to investigate and plan the reconfiguration of the existing MEP systems.

Storage Bar
• Continue to relocate existing utilities.
• Finish mass excavation.
• Dig footings.


Retaining wall footings/steps.


Parking area columns.


Gallery joist/decking/skylight framing.

No comments:

Post a Comment