Tuesday, September 22, 2009

Construction Updates from Holder

Here's this week's construction update from Holder:

Sept. 18, 2009

Current week - Activities/Issues:

New Gallery / Connector
• Completed the skylight structural steel support.
• Poured balance of concrete columns.
• Poured 1st half of the signage wall.
• Started below grade waterproofing.
• Started the 1st floor masonry walls.
• Prepared for elevated slab pours.

Existing Building Renovations
• Complete the emergency power relocates.

Storage Bar
• Started to mass excavate under new structure.
• Relocated the existing domestic water.

Next week - Activities/Issues:

New Gallery / Connector
• Pour the 2nd half of the signage wall.
• Pour the West end of the elevated gallery slab.
• Pour the East end of the elevated gallery slab.
• Start removing the existing brick façade at the connector.

Existing Building Renovations
• Finish the balance of the interior demolition.

Storage Bar
• Complete mass excavation.
• Start digging footings.


Structure view from Carlton Street


1st half of signage wall poured


1st-floor masonry

No comments:

Post a Comment