Construction Updates from Holder

Here are the latest updates on construction of Phase II of GMOA from Holder Construction, for the week ending January 8, 2010.

Current week - Activities/Issues:
New Gallery / Connector
• Started brick 1st floor of gallery.
• Continued to install exterior limestone façade.
• Continued MEP overhead on 1st floor.
• Continued connector SOG waterproofing.
• Continued the connector roofing.
• Poured 1st Floor Connector.
• Started Curtainwall connector.
• Damp proof the 1st floor CMU.
• Start Metal panels on skylights.
• Reworked brick on connector.

Storage Bar
• MEP R/I S.O.G. Complete.
• Start the exterior concrete wall waterproofing / vapor barrier.

Next week - Activities/Issues:
New Gallery / Connector
• Continue working on connector roofing.
• Continue to install the exterior vapor barrier and limestone.
• Continue MEP overhead in the gallery.
• Pour elevated slab.
• Installing interior vapor barrier gallery.

Existing Building Renovations
• Continue with the MEP overhead rough-in.
• Start layout of drywall.

Storage Bar
• Start Exterior CMU

Limestone continuation on west side of building

Brick inside parking deck

2nd-floor gallery skylight wall