Monday, February 01, 2010

Construction Updates from Holder

Here's this week's construction update from Holder, for the week ending January 29, 2010.

Current week - Activities/Issues:
New Gallery / Connector
· Installing 1st Floor Brick
· Continue MEP overhead 1st Floor
· Completed MEP overhead 2nd Floor
· Continue Gallery interior wall vapor barrier
· Continue working on connector roof
· Started rework of structural steel
· Reworking and insulating existing roof
· Painted and block filled cmu walls

Existing Building Renovations
· Continue MEP overhead rough-in
· Continue framing of walls
· Hanging, mudding and finishing drywall

Storage Bar
· Continue the exterior concrete wall waterproofing / vapor barrier.
· Framing exterior walls and sheathing
· Back-filling wall

Next week - Activities/Issues:
New Gallery / Connector
· Continue drywall on 2nd Floor
· Continue installing brick 1st Floor
· Curtain wall framing and installing punch openings
· Setting external stairs
· Mud, tape and finish drywall
· Framing hard ceilings
· Digging footings and pouring in courtyard
· Continue exterior limestone work
· Start rolled on vapor barrier and exterior sheathing

Existing Building Renovations
· Continue hanging drywall
· Continuing installation of new AHU M-8 and new duct

Storage Bar
· Continue cmu walls on exterior foundation
· Backfilling exterior structure walls
· Loading new roof with materials and begin moving existing roof on the Art Building.

Waterproofing at storage bar

Storage bar progress

New footings at sculpture garden