Monday, April 26, 2010

Construction Updates from Holder

Here's the weekly construction update, for the week ending April 23, 2010:

Current week - Activities/Issues:
New Gallery / Connector
• Installed all electric floor boxes in the gallery.
• Finished ceilings and painted walls in the connector.

Existing Building Renovations
• Finishing ceilings and painting walls.
• Completed the waterproofing repairs to the existing North wall on 3rd floor.

Storage Bar
• Completed the vapor barrier / spray insulation on the 2nd floor.
• Started interior framing / hanging drywall on second floor.

Site / Sculpture Garden
• Continuing to excavate and remove rock for the cistern tanks.
• Installed the irrigation mains and built up soils in the sculpture garden.

Next week - Activities/Issues:
New Gallery / Connector
• Install wood flooring sleeper system and complete finish mock-up.

Existing Building Renovations
• Start below SOG vapor barrier at the east alternate entry.
• Start roofing / gutters for the east alternate entry.
• Continue to finish walls and prime paint.

Storage Bar
• Finish roof installation on the 2nd floor.
• Hang drywall in the 2nd floor.

Site / Sculpture Garden
• Continue to excavate cistern tank and water pump tank.
• Install the water vault for the fountain in the sculpture garden.
• Complete concrete hardscape mock-up.

Floor box installation in gallery

Existing 1st-floor interior ceiling framing

Connector finishes and ceiling progress