Tuesday, June 01, 2010

Construction updates from Holder

Here are the updates from Holder for the past two weeks.

Week ending on 5/21:

New Gallery/Connector
  • Installing wood flooring in gallery
  • Installing terrazzo flooring in connector
  • Final water test for skylights
Existing Building Renovations
  • Continue to finish painting existing walls
  • Installing millwork/shelving
  • Complete east entry revisions
Storage Bar
  • Repaired spray fire proofing
  • Coated the fireproofing
  • MEP trim out
Site/Sculpture Garden
  • Poured stairs, ramps and walk pads
  • Excavating cistern
Week ending on 5/28:

New Gallery/Connector
  • Sanding and finishing wood flooring in gallery
  • Installing floor expansion joint in connector
  • Finishing terazzo base and grout
Existing Building Renovations
  • Continue to finish painting existing walls
  • Installing millwork/shelving
  • MEP final trim out
  • Installing doors and hardware
Storage Bar
  • Completed the repairing of spray fire proofing
  • Continue MEP trim out
Site/Sculpture Garden
  • Poured stairs, ramps and walk pads and continued installing planting beds
  • Completed excavating of cistern
Next week - Activities/Issues

New Gallery/Connector
  • Installing handrails on connector stairs
  • Start painting structural steel
  • Finish terrazzo
Existing Building Renovations
  • Fireproof structural steel on east entry
  • Continue interior wall framing of east entry
Storage Bar
  • Finish painting of storage areas
Site/Sculpture Garden
  • Set cistern tank and piping
  • Plant trees

Terrazzo installation in lobby


Gallery wood flooring


Sculpture garden walk paths

Check out the construction webcam here and keep reading the blog for updates!