Tuesday, June 22, 2010

Construction Updates from Holder

Here are the construction updates from the week of June 18.

Current week - Activities/Issues:

New Gallery/Connector
  • Building removable walls
  • Bondo monumental stairs
  • Started monumental stair treads
Existing Building Renovations
  • Installing first floor lobby ceiling
  • Refinish gallery 251 wood floor
  • MEP final trim out
  • Install linoleum in catering kitchen
Storage Bar
  • Installing punch window opening on third floor
  • Completed MEP trim out
Site/Sculpture Garden
  • Placed granite treads
  • Backfilling cistern tanks
  • Start trellis installation
Next week - Activities/Issues:

New Gallery/Connector
  • Complete removable walls
  • Complete stair handrails
Existing Building Renovations
  • Complete installation of catering kitchen millwork
  • Finishes in first floor lobby
Storage Bar
  • Final paint
Site/Sculpture Garden
  • Continue stainless steel fencing
  • Continue to install plants

Removable walls construction


Driveway asphalt progress


Catering kitchen millwork installation

No comments:

Post a Comment