Tuesday, July 06, 2010

Construction Updates from Holder

Here are the Phase II construction updates from the week of July 2.

Current week - Activities/Issues:

New Gallery/Connector
  • Readjusting skylight well walls
  • Built out A/V and security closet
Existing Building Renovations
  • Installed glass panels behind reception desk
  • Installed first floor lobby ceiling tiles
  • MEP trim out catering kitchen
Storage Bar
  • HVAC duct work adjustments to raise light fixtures
Site/Sculpture Garden
  • Started running water fountain
  • Installed metal panels at connector
  • Installed conductor heads and down spouts
Next week - Activities/Issues:

New Gallery/Connector
  • Finish skylight repairs
  • Set display case cabinets
Existing Building Renovations
  • Set reception desk millwork
  • Install hanging fin glass
Storage Bar
  • Seal concrete floor
Site/Sculpture Garden
  • Complete lattice fence
  • Start landscaping south gallery

Metal panels installed above connector

Lattice fence in parking garage progress

A/V room progress