Tuesday, September 07, 2010

Construction Updates from Holder

Here are the updates from the week of September 3.


Current week - Activities/Issues:


Demolition of Figgie’s Café

Installing interior/exterior signage

Commissioning of Cistern System

Working on punch list items

Working on miscellaneous millwork items

Started barrel roof coping repairs

Next week - Activities/Issues:

Finalize test and balance report/final sign off

Continue w/ barrel roof repairs

Work on punch list throughout the building

Continue installation of interior signage

Finish window blinds

Complete misc. millwork items/loose FFE


Way Signage installation throughout building

Glass Inserts installed on Main Lobby GMOA Logo

Figgie's Café Renovation Progress

No comments:

Post a Comment