Current week - Activities/Issues:
New Gallery / Connector
· Installing the connector roofing and flashing.
· Hanging drywall walls and ceilings in gallery.
· Starting to tape and finish gallery walls.
· Framing / hanging main Gallery space ceilings.
· Coordinating MEP overhead trim out.
· Poured the connector elevated slab.
Existing Building Renovations
· Continue MEP overhead rough-in
· Tape and finish drywall walls
· Ongoing rework existing roof
Storage Bar
· Completed the exterior concrete wall waterproofing / vapor barrier.
· Started exterior brick façade.
Next week - Activities/Issues:
New Gallery / Connector
· Continue to hang, tape finish drywall walls & ceilings in gallery
· Continue to pour footings and walls in the sculpture garden area.
· Finish gallery exterior limestone.
· Start erecting the monumental connector stair.
· Install connector curtainwall system.
· Start connector MEP overhead rough-in.
Existing Building Renovations
· Tape & finish walls.
· Frame ceilings.
· Prime paint walls.
Storage Bar
· Continue exterior CMU and brick walls.
· Start new roof on storage bar
· Finish MEP overhead rough-in.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEi_YxRjE-yOaxx_5OCe3c9UsCY5qPIygkjDx-LiDmT1GQXWS_DYRdkxzStqOKmahTQZCfnfqAvW2c_r0FEfih0SmbHoCl0v0Vy-3X6tQBf25pIoe5UfqTKk50Z2qWaXemb3bY9i/s400/Sculpture+garden+progress.jpg)
Sculpture garden progress
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhK4KjJDWaRj81lK3kRfJ7PUT2f3ugMniODCaf2d4f8wv2Jd3k5OZEYWjVVjkJDVE5dHelcRqZP6tftVrLMScat9k08JClgUz4fiR9kj75Hn0f9aRA-gWE7Sxs7GHRNfj04VNco/s400/Interior+gallery+progress.jpg)
Interior gallery progress
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhf8omtPBIbIZHVRRNWhKTDAEp6YMKnXoQAw_nsaslh04JklShA1A9OuWcpXSMXcEpEoYnFrbrUwsczLzNUgDOCatz8l-iRjrCjuNBeWtBsyWsYfQ5epa-cxci-8NdLPvjN3ihG/s400/Connector+elevated+slab.jpg)
Connector elevated slab
No comments:
Post a Comment