Monday, February 22, 2010

Construction Updates from Holder

Here's your construction update on Phase II for the week ending February 19, 2010.

Current week - Activities/Issues:
New Gallery / Connector
· Installing the connector roofing and flashing.
· Hanging drywall walls and ceilings in gallery.
· Starting to tape and finish gallery walls.
· Framing / hanging main Gallery space ceilings.
· Coordinating MEP overhead trim out.
· Poured the connector elevated slab.

Existing Building Renovations
· Continue MEP overhead rough-in
· Tape and finish drywall walls
· Ongoing rework existing roof

Storage Bar
· Completed the exterior concrete wall waterproofing / vapor barrier.
· Started exterior brick façade.

Next week - Activities/Issues:
New Gallery / Connector
· Continue to hang, tape finish drywall walls & ceilings in gallery
· Continue to pour footings and walls in the sculpture garden area.
· Finish gallery exterior limestone.
· Start erecting the monumental connector stair.
· Install connector curtainwall system.
· Start connector MEP overhead rough-in.

Existing Building Renovations
· Tape & finish walls.
· Frame ceilings.
· Prime paint walls.

Storage Bar
· Continue exterior CMU and brick walls.
· Start new roof on storage bar
· Finish MEP overhead rough-in.

Sculpture garden progress

Interior gallery progress

Connector elevated slab