Monday, January 11, 2010

Construction Updates from Holder

Here are the latest updates on construction of Phase II of GMOA from Holder Construction, for the week ending January 8, 2010.

Current week - Activities/Issues:
New Gallery / Connector
• Started brick 1st floor of gallery.
• Continued to install exterior limestone façade.
• Continued MEP overhead on 1st floor.
• Continued connector SOG waterproofing.
• Continued the connector roofing.
• Poured 1st Floor Connector.
• Started Curtainwall connector.
• Damp proof the 1st floor CMU.
• Start Metal panels on skylights.
• Reworked brick on connector.

Storage Bar
• MEP R/I S.O.G. Complete.
• Start the exterior concrete wall waterproofing / vapor barrier.

Next week - Activities/Issues:
New Gallery / Connector
• Continue working on connector roofing.
• Continue to install the exterior vapor barrier and limestone.
• Continue MEP overhead in the gallery.
• Pour elevated slab.
• Installing interior vapor barrier gallery.

Existing Building Renovations
• Continue with the MEP overhead rough-in.
• Start layout of drywall.

Storage Bar
• Start Exterior CMU

Limestone continuation on west side of building

Brick inside parking deck

2nd-floor gallery skylight wall

No comments: