Monday, June 28, 2010

Construction Updates from Holder

Here are the construction updates from the week of June 25.

Current week - Activities/Issues:

New Gallery/Connector
  • Removable walls complete
  • Reworking doors
  • Install glass and stainless steel handrails
Existing Building Renovations
  • Installing first floor lobby ceiling
  • Re-finish gallery 251 wood floor
  • Install linoleum in catering kitchen
Storage Bar
  • Installing punch window opening on third floor
  • Completed MEP trim out
  • Start punch list
Site/Sculpture Garden
  • Finish grading of cistern
  • Working on installing sidewalks
  • Start trellis installation
Next week - Activities/Issues:

New Gallery/Connector
  • Complete grouting of floors
  • Complete stair handrails
Existing Building Renovations
  • Complete installation of catering kitchen millwork
  • Finishes in first floor lobby
Storage Bar
  • Final paint
Site/Sculpture Garden
  • Continue stainless steel fencing
  • Continue to install plants

Ceiling installation in parking garage

Sculpture garden water feature

Glass installation on stair railings

No comments: