Tuesday, November 10, 2009

Updates from Ronnie, part 2

Here are the construction updates from this most recent week, ending Nov. 6, 2009.

Current week - Activities/Issues:

New Gallery / Connector
• Poured Gallery Slab on Grade
• Installed sheathing at the exterior gallery walls.
• Installed spray fireproofing and spray insulation.
• Continued to erection connector steel.
• Continued with connector roof decking.
• Continued to waterproof and backfill the concrete retaining walls.

Existing Building Renovations
• Changed the temporary chilled water lines to new lines for 1st floor mechanical room.

Storage Bar
• Completed mass excavation to subgrade.
• Formed and poured 2/3 of the concrete footings.

Next week - Activities/Issues:

New Gallery / Connector
• Complete the sheathing of the exterior gallery walls.
• Mobilize roofing materials and begin sheathing and vapor barrier.
• Start spray fireproofing at the gallery parking area.
• Complete the exterior wall air barrier mock-up.
• Install shoring needed to complete connector tie-into existing building.
• Start the grading and drainage systems at the sculpture garden.

Existing Building Renovations
• Continue to demo / relocating the existing building systems.

Storage Bar
• Finish storage bar concrete footing/foundations.
• Start forming and pouring concrete retaining walls.

Storage bar mass excavation and footing excavation

Retaining wall waterproofing and backfill

Exterior sheathing/spray insulation and fireproofing

No comments: