Monday, April 19, 2010

Construction Updates from Holder

Here's the update for the week that ended April 16, 2010:

Current week - Activities/Issues:
New Gallery / Connector
• Finishing MEP Trim-out in the gallery
• Started electrical / V/D floor boxes for the gallery floor
• Continued to frame & finish ceilings in the connector
• Completed brick in the connector
• Started excavation for the cistern

Existing Building Renovations
• Installed ceiling grid on the 3rd floor
• Started repairs to the existing north wall & windows on the 3rd floor
• Completed new windows & sunshades on the South side of the 3rd floor
• Erected structural steel for the east entry alternate

Storage Bar
• Finished and cleaned all the exterior brick
• Started the roof tie-in at the 2nd floor
• Installed the exterior stairwell

Next week - Activities/Issues:
New Gallery / Connector
• Run AHU#6 to condition the gallery space
• Finish floor box rough-in in the gallery
• Hang doors in the gallery
• Finish ceilings in the connector and remove the scaffolding

Existing Building Renovations
• Start below SOG vapor barrier at the east alternate entry
• Start roofing / gutters for the east alternate entry
• Continue with the existing North wall repairs
• Start prime painting the 2nd and 3rd floors

Storage Bar
• Finish roof installation on the 2nd floor
• Finish ceilings and prime walls on the 3rd floor
• Finish vapor barrio and wall frame on the 2nd floor

Storage bar exterior stairwell

Cistern excavation

Alternate east entry structural steel assembly

No comments: