Construction Updates from Holder

Here's the construction update from the week of Aug. 28.

Current week - Activities/Issues:

New Gallery / Connector
• Complete the Seq#2 Structural Steel
• Complete the 2nd level decking for Seq#1 & #2.
• Continued to install roof joists.
• Started roof decking.
• Poured concrete columns at the parking area.
• Poured retaining wall footings.

Existing Building Renovations
• Removed main stairwell concrete foundation.
• Completed selective demolition on the ground floor.
• 95% complete with selective demolition on the 2nd floor.
• 95% complete with selective demolition on the 3rd floor.

Storage Bar
• Ran the exterior emergency power into the mechanical room.

Next week - Activities/Issues:

New Gallery / Connector
• Install roof joists.
• Install roof decking.
• Continue to pour concrete columns.
• Continue to pour retaining wall footings.
• Form and pour retaining walls.

Existing Building Renovations
• Investigate existing MEP systems.
• Develop plan to start MEP demolition of existing systems.

Storage Bar
• Continue to relocate emergency power.

And here are the photos Holder attached:



Retaining wall footings



Gallery steels, joists and decking



Selective demolition on the 2nd floor

Starting tomorrow, staff will be touring some of the progress on the building, with more photos to come.