Construction Updates from Holder

Here's the construction update from Holder for the week ending February 26:

Current week - Activities/Issues:
New Gallery / Connector
· Frame connector walls
· Hanging drywall walls and ceilings in gallery
· Starting to tape and finish gallery walls
· Framing / hanging main Gallery space ceilings
· Coordinating MEP overhead trim out

Existing Building Renovations
· Continue MEP overhead rough-in
· Hang hard ceiling
· Prime and paint walls

Storage Bar
· Framing interior walls
· Started exterior brick façade
· Spray foam insulation in walls

Next week - Activities/Issues:
New Gallery / Connector
· Install curtain wall glass
· Start connector exterior brick
· Backfill sculpture garden walls
· Start layout/digging bio-retention pond

Existing Building Renovations
· Tape & finish walls.
· Prime paint walls.
· Demo walls and install structural steel frames for new windows

Storage Bar
· Continue exterior CMU and brick walls.
· Finish MEP overhead rough-in.

Sculpture garden progress

Connector interior progress

Connector exterior progress