Friday, March 26, 2010

Construction Updates from Holder

Last week's weekly report slipped through the cracks, but we just got it, along with this week's, so here they both are. The first is for the week ending March 19, 2010:

Current week - Activities/Issues:
New Gallery / Connector
• Framing connector walls/soffit
• Completed MEP overhead trim out
• Installing glass at the connector curtainwall
• Backfill sculpture garden walls
• Start layout/digging bio-retention pond

Existing Building Renovations
• Tape and finish walls and ceilings
• MEP rough-in hard ceilings
• MEP rough-in acoustical ceilings

Storage Bar
• Framing and hanging interior walls
• Completed exterior brick façade

Next week - Activities/Issues:
New Gallery / Connector
• Complete curtain wall glass
• Continue framing walls and soffits
• Turn HVAC units on in gallery
• Build scaffold in connector
• Hanging walls in connector
• Installing sewer line at east entry
• Demo existing brick wall at east entry

Existing Building Renovations
• Tape & finish walls and ceilings
• Start priming interior walls

Storage Bar
• Finish MEP overhead rough-in.
• Continue Framing interior walls
• Installing windows
• Back filling storage bar

And here are the associated images:

East entry progress

Sculpture garden progress

Sculpture garden curtain wall

Now, here's the report for the week that just ended, the week of March 26, 2010:

Current week - Activities/Issues:
New Gallery / Connector
· Complete curtain wall at connector
· Complete framing walls and soffits at connector
· Start hanging walls in connector
· Turn on HVAC units in gallery

Existing Building Renovations
· Install sanitary sewer line at east entry
· Start brick demo at east entry
· Tape and finish walls and ceilings
· Start priming interior walls

Storage Bar
· Finish MEP overhead rough-in
· Install windows
· Framing interior walls
· Backfill storage bar

Next week - Activities/Issues:
New Gallery / Connector
· MEP rough-in soffits at connector
· Hang walls in connector
· Hang ceilings in connector
· Prime walls/ceilings in gallery

Existing Building Renovations
· Complete brick demo at new east entry
· Start concrete footings at new east entry
· Continue priming interior walls

Storage Bar
· Finish MEP overhead rough-in
· Install 3rd floor ceiling grid
· Frame 2nd floor interior walls

And here are its pictures:

Storage bar exterior

Gallery parking ceiling framing

Gallery interior progress

No comments: