Monday, July 12, 2010

Construction Updates from Holder

Here are the Phase II construction updates from the week of July 9.


Current week - Activities/Issues:


New Gallery / Connector


Mud tape and finish walls and ceiling

Complete grout of tile


Existing Building Renovations


Installed glass panels behind reception desk

Installed 1st floor lobby ceiling tiles

MEP trim out catering kitchen

Storage Bar


Completed HVAC duct work adjustments to raise light fixtures

Site / Sculpture Garden

Complete all misc. handrails

Completed final grading of site

Reinstalling pavers at east entry

Completing planting of plants


Next week - Activities/Issues:


New Gallery / Connector

Finish rails

Begin punchlist


Existing Building Renovations

Final cleaning


Storage Bar

Seal concrete floor


Site / Sculpture Garden


Complete lattice fence

Continue landscaping south gallery


Grouting of Tile in Main Lobby

Glass Inserts along Connector Stair Railings

Catering Kitchen Progress

No comments: