Showing posts with label construction. Show all posts
Showing posts with label construction. Show all posts

Monday, September 27, 2010

Construction Updates from Holder

Here are the construction updates from the week of September 24, 2010.

Current week - Activities/Issues:
  • Continue renovation of former café space
  • Continue installing gallery signage
  • Working on punch list items
  • Working on miscellaneous millwork items
  • Working on barrel roof coping
  • Poured concrete wall at sculpture garden fountain
  • Poured ramp at loading dock
Next week - Activities/Issues:
  • Continue working on barrel roof coping
  • Work on punch list throughout the building
  • Continue installation of remaining interior signage
  • Continue installation of skylight shades
  • Complete miscellaneous millwork items/loose FFE
  • Continue renovation of former café space
  • Continue final cleaning and touchups
  • Install handrails to newly poured ramp at loading dock

Concrete wall at fountain in sculpture garden


Ramp added at loading dock

Friday, September 17, 2010

Construction Updates from Holder

Here's the report from Holder for the week ending today, September 17, 2010.

Current week - Activities/Issues:
• Continue renovation of Figgie’s Café
• Continue installing gallery signage
• Working on punch list items
• Working on miscellaneous millwork items
• Continued barrel roof coping repairs

Next week - Activities/Issues:
• Finalize test and balance report/final sign off
• Continue w/ barrel roof coping repairs
• Work on punch list throughout the building
• Continue installation of remaining interior signage
• Continue installation of skylight shades
• Complete misc. millwork items/loose FFE
• Continue renovation of Figgie’s Café
• Continue final cleaning and touchups

Window blinds installation

Wall repainting and touch-ups

Main lobby signage installation

Concrete wall repairs at fountain in garden

Friday, September 10, 2010

Construction Updates from Holder

Here are the week's construction updates from Holder on the building:

Current week - Activities/Issues:
• Continue renovation of Figgie’s Café
• Continue installing interior signage
• Working on punch list items
• Working on miscellaneous millwork items
• Continued barrel roof coping repairs

Next week - Activities/Issues:
• Finalize test and balance report/final sign off
• Continue w/ barrel roof coping repairs
• Work on punch list throughout the building
• Continue installation of interior signage
• Finish window blinds
• Continue installation of skylight shades
• Complete misc. millwork items/loose FFE
• Continue renovation of Figgie’s Café


Skylight shades installation progress

Wood paneling installed around existing gallery entrances

New gallery signs installed

Glass countertop installation on lobby reception desk

Tuesday, September 07, 2010

Construction Updates from Holder

Here are the updates from the week of September 3.


Current week - Activities/Issues:


Demolition of Figgie’s Café

Installing interior/exterior signage

Commissioning of Cistern System

Working on punch list items

Working on miscellaneous millwork items

Started barrel roof coping repairs

Next week - Activities/Issues:

Finalize test and balance report/final sign off

Continue w/ barrel roof repairs

Work on punch list throughout the building

Continue installation of interior signage

Finish window blinds

Complete misc. millwork items/loose FFE


Way Signage installation throughout building

Glass Inserts installed on Main Lobby GMOA Logo

Figgie's Café Renovation Progress

Friday, August 20, 2010

Construction Updates from Holder

Good afternoon. Here's the latest construction update from Holder.

Current week - Activities/Issues:
• Installing Skylight shades
• Installing interior/exterior signage
• Completed painting AESS Exposed Steel
• Working on punch list items
• Working on miscellaneous millwork items
• Sealing concrete floors
• Functional testing of building systems

Next week - Activities/Issues:
• Start demolition and build out of café
• Terrazzo tile repairs
• Work on punch list throughout the building
• Continue installation of interior signage
• Finish window blinds
• Complete misc. millwork items
• Design team punch galleries, connector and lobby

South elevation exterior with landscaping

Gallery display cabinets

Exterior lights on site wall

Exterior concrete benches

Tuesday, August 17, 2010

Construction Updates from Holder

Here are the construction updates from the week of August 13.

Current week - Activities/Issues:

Installing Skylight shades

Installing interior/exterior signage

Painting AESS Exposed Steel

Working on punchlist items

Working on miscellaneous millwork items

Sealing concrete floors

Functional testing of building systems


Next week - Activities/Issues:

Sealing concrete floors

Terrazzo tile repairs

Work on punchlist

Continue installation of interior signage

Finish window blinds

Complete misc. millwork items

Design team punch galleries, connector and lobby



Interior Lobby GMOA Logo

Interior Gallery Signage

Connector Glass Railings & Tile

Friday, August 06, 2010

Construction Updates from Holder

Here's your weekly construction update. Things are looking more and more finished as signage is being installed.

Current week - Activities/Issues:
• Installing Skylight shades
• Installing interior/exterior signage
• Sanding of intumescent
• Installed cane detection rail
• Installed east entry awning/metal panels
• Striped parking lot
• Working on punchlist items
• Cistern/BRAE Pump owner training
• Poured balance of sidewalk by loading dock entrance

Next week - Activities/Issues:
• Seal concrete floors
• Work on punchlist
• Continue installation of interior signage
• Finish window blinds
• Complete misc. millwork items
• Start functional testing of building systems

South elevation landscaping

Interior glass door signage

Exterior signage installed

East entry awning installation

Virtual GMOA



Larry Forte, our Daura Art Handler and man of many talents, has been hard at work building this fabulous foam-core model of the expanded and renovated building so our curators will be able better to visualize both exhibitions and the installation of the permanent collection. It's not quite the same as walking through the real thing, but we also can't take the top off the real museum.

Monday, August 02, 2010

Construction Updates from Holder

Here are the construction updates from the week of July 30th.


Current week - Activities/Issues:


New Gallery / Connector

Installing intumescent paint

Final finish on wood floors

Installing Skylight shades

Existing Building Renovations

Walking off Completion List

Storage Bar

Walking off Completion List

Site / Sculpture Garden

Installed BRAE cistern pump system

Planted trees

Striping/wheel stops in parking area


Next week - Activities/Issues:


New Gallery / Connector

Final clean

Signage

Existing Building Renovations

Final cleaning

Walk off completion list

Install aluminum awning/metal panels

Storage Bar

Walk off Completion list

Site / Sculpture Garden

Walk off Completion list


Lights installed in parking garage area

Parking garage skylight progress

Names etched in sculpture garden wall


Monday, July 26, 2010

Construction Updates from Holder

Here are the construction updates from the week of July 23.

Current week - Activities/Issues:

New Gallery/Connector
  • Starting intumescent paint
  • Complete handrails on connector stairs
  • Installing skylight shades
Existing Building Renovations
  • Final clean
  • Continue completion list
Storage Bar
  • Complete final clean
  • Begin completion list
Site/Sculpture Garden
  • Completed all miscellaneous handrails
  • Completing planting of plants
  • Water feature adjustments
Next week - Activities/Issues:

New Gallery/Connector
  • Finish rails
  • Begin signage
Existing Building Renovations
  • Final cleaning
Storage Bar
  • Seal concrete floor
Site/Sculpture Garden
  • Continue punchlist

Print study room with millwork

Terrazzo tile floor installed in connector

Hanging glass in lobby installed

Wednesday, July 21, 2010

Construction Updates from Holder

Here are the construction updates for the week of July 16.

Current week - Activities/Issues:

New Gallery/Connector
  • Starting paint of structure steel
  • Complete handrails on connector stairs
  • Installing millwork
Existing Building Renovations
  • Final clean
  • Continue completion list
Storage Bar
  • Complete final clean
  • Begin completion list
Site/Sculpture Garden
  • Completed all miscellaneous handrails
  • Completing planting of plants
Next week - Activities/Issues:

New Gallery/Connector
  • Finish rails
  • Begin punchlist
Existing Building Renovations
  • Final cleaning
Storage Bar
  • Seal concrete floor
Site/Sculpture Garden
  • Complete lattice fence
  • Continue landscaping south gallery

South elevation landscaping

Brick pavers installed at east entry

Parking control equipment installed

Monday, July 12, 2010

Construction Updates from Holder

Here are the Phase II construction updates from the week of July 9.


Current week - Activities/Issues:


New Gallery / Connector


Mud tape and finish walls and ceiling

Complete grout of tile


Existing Building Renovations


Installed glass panels behind reception desk

Installed 1st floor lobby ceiling tiles

MEP trim out catering kitchen

Storage Bar


Completed HVAC duct work adjustments to raise light fixtures

Site / Sculpture Garden

Complete all misc. handrails

Completed final grading of site

Reinstalling pavers at east entry

Completing planting of plants


Next week - Activities/Issues:


New Gallery / Connector

Finish rails

Begin punchlist


Existing Building Renovations

Final cleaning


Storage Bar

Seal concrete floor


Site / Sculpture Garden


Complete lattice fence

Continue landscaping south gallery


Grouting of Tile in Main Lobby

Glass Inserts along Connector Stair Railings

Catering Kitchen Progress