Here are the construction updates from the week of September 24, 2010.
Current week - Activities/Issues:
- Continue renovation of former café space
- Continue installing gallery signage
- Working on punch list items
- Working on miscellaneous millwork items
- Working on barrel roof coping
- Poured concrete wall at sculpture garden fountain
- Poured ramp at loading dock
Next week - Activities/Issues:
- Continue working on barrel roof coping
- Work on punch list throughout the building
- Continue installation of remaining interior signage
- Continue installation of skylight shades
- Complete miscellaneous millwork items/loose FFE
- Continue renovation of former café space
- Continue final cleaning and touchups
- Install handrails to newly poured ramp at loading dock
Ramp added at loading dock