Tuesday, August 11, 2009

Construction Updates from Holder






As of Friday, August 7, here's the report from Holder:

Current week - Activities/Issues:

New Gallery / Connector
• Excavated and poured concrete footings.
• Installed site utilities.
• Placed sub-grade and asphalt binder under the new gallery.
• Demolished the existing canopy.
• Steel erector and crane mobilized.
• Erected structural steel columns and beams.
• Poured the architectural concrete wall mock-up

Existing Building Renovations
• Demolished the ceiling of the main stairwell.
• Removed the existing utilities at the main stairwell.

Storage Bar
• Installed temporary chilled water piping inside the building.

Next week - Activities/Issues:

• Continue to place footings.
• Continue to install site utilities.
• Continue with structural steel erection.
• Demo exterior skin of the main stairwell.
• Install the temporary underground CW piping.
• Tie into the main campus CW loop system.
• Begin to install noise & dust control in the existing building.

Inspections/Testing:
• Soil compaction.
• Rebar inspections / concrete testing.
• Sub-grade / asphalt inspections.
• Utility / material Inspections.

And we should have the streaming webcam from the construction site up on our Web site any hour now, so you can watch the bulldozers roll around.

No comments: