Tuesday, August 25, 2009
Construction Updates from Holder
Here's the update from the week of Aug. 21:
Current week - Activities/Issues:
New Gallery / Connector
• Finished decking Seq#1.
• Finished site utilities around the gallery.
• Erecting Seq#2 steel and decking.
• Installing roof joists.
Existing Building Renovations
• Finished demolition of the main stairwell skin.
• Installed dust control on the ground floor, level 2 and level 3.
• Removed the ceiling on the ground floor.
Storage Bar
• Backfilled around the campus loop tie-in.
Next week - Activities/Issues:
New Gallery / Connector
• Finish Seq#2 structural steel erection.
• Install Seq#2 decking.
• Finish roof joists.
• Start roof decking.
Existing Building
Remove the main stairwell concrete foundation.
• Start selective demo on 2nd floor.
• Start selective demo on 3rd floor.
Storage Bar
• Relocate / temporary existing electrical utilities.
• Start mass excavation under building footprint.