For the week ending Oct. 23, 2009:
Current week - Activities/Issues:
New Gallery / Connector
• Installed vapor barrier and roof sheathing at skylights.
• Completed the large concrete retaining walls.
• Framed exterior parapet walls.
• Completed SOG below grade vapor barrier.
• Continued erecting of the connector structural steel.
• Started decking at the connector roof.
• Started exterior beam and column spray fireproofing.
• Started sheathing exterior gallery walls.
• Started waterproofing the concrete retaining walls.
Existing Building Renovations
• Continued with the CW piping installation inside the 1st floor mechanical room.
• Re-routed the domestic water lines into the 1st floor mechanical room.
Storage Bar
• Completed the installation of the new chilled water lines.
• Started cut/fill excavation of the building footprint to sub-grade.
Next week - Activities/Issues:
New Gallery / Connector
• Pour gallery SOG at the two mechanical rooms.
• Continue sheathing the exterior gallery walls.
• Continue spray fireproofing exterior beams and columns.
• Start the spray foam insulation at exterior beams and columns.
• Build the exterior wall air barrier mock.
• Continuing erecting the connector structural steel.
Existing Building Renovations
• Continue to demo / relocating the existing building systems.
Storage Bar
• Start to excavate and pour concrete footings.