Current week - Activities/Issues:
New Gallery / Connector
• Continued Spray Fireproofing under 2nd floor slab.
• Continued framing for the Hardie Board soffit panels.
• Installed sheathing at the exterior gallery walls.
• Started the roof sheathing and vapor barrier.
• Installed below-grade damproofing for SOG exterior concrete.
• Completed shoring at the connector steel beams.
• Started to install the sculpture garden storm drainage.
• Installed the exterior wall vapor barrier mock-up.
Existing Building Renovations
• Planned for temporary walls at the East Alternate Entry.
Storage Bar
• Continued to formed and poured concrete footings.
• Started to form and pour concrete retaining walls.
Next week - Activities/Issues:
New Gallery / Connector
• Continue the sheathing of the exterior gallery walls.
• Continue to install roof sheathing and vapor barrier.
• Continue to spray fireproofing at the gallery parking area.
• 1st major deliveries of limestone for the exterior skin.
Existing Building Renovations
• Start temporary walls for the East Alternate entry.
Storage Bar
• Finish storage bar concrete footing/foundations.
• Continue forming and pouring concrete retaining walls.
Started roof sheathing and vapor barrier
Gallery sheathing at exterior skin