Current week - Activities/Issues:
New Gallery / Connector
• Continued to install skylights.
• Continued to install Gallery TPO roof membrane.
• Continued to install exterior wall vapor barrier.
• Continued to install exterior limestone façade.
• Completed CMU masonry on the 1st floor.
• Started MEP overhead on 1st floor.
• Completed the connector structure.
• Started connector SOG waterproofing.
Existing Building Renovations
• Completed the demo of the existing east entry.
• Starred the mechanical overhead in the Kennedy/Alston gallery.
Storage Bar
• Started erecting structural steel.
• Completing structural tie-ins to the existing building.
Next week - Activities/Issues:
New Gallery / Connector
• Complete the TPO roofing system and parapets.
• Continue to install the exterior vapor barrier and limestone.
• Start spray fireproofing in the gallery.
• Start MEP overhead in the gallery.
• Continue to pour the connector SOG and elevated deck.
• Start the connector roofing.
• Start layout for connector curtainwall.
Existing Building Renovations
• Start MEP overhead rough-in.
Storage Bar
• Continue erecting structural steel.
Storage bar structure
Skylights installed
Exterior limestone skin
No comments:
Post a Comment