Current week - Activities/Issues:
New Gallery / Connector
• Framing connector walls/soffit
• Coordinating MEP overhead trim out
• Installing glass at the connector curtainwall
• Backfill sculpture garden walls
• Start layout/digging bio-retention pond
Existing Building Renovations
• Tape and finish walls and ceilings
• MEP rough-in hard ceilings
• MEP rough-in acoustical ceilings
Storage Bar
• Framing interior walls
• Hang interior walls
• Continue exterior brick façade
Next week - Activities/Issues:
New Gallery / Connector
• Complete curtain wall glass
• Continue framing walls and soffits
• Complete connector roof
• Start MEP wall rough-in
Existing Building Renovations
• Tape & finish walls and ceilings
• Start priming interior walls
Storage Bar
• Complete exterior CMU and brick walls.
• Finish MEP overhead rough-in.
• Continue framing interior walls

Storage bar exterior

Sculpture garden progress

Sculpture garden curtain wall