Friday, March 12, 2010

Construction Updates from Holder

Here's your update from Holder for the week ending today (March 12).

Current week - Activities/Issues:
New Gallery / Connector
• Framing connector walls/soffit
• Coordinating MEP overhead trim out
• Installing glass at the connector curtainwall
• Backfill sculpture garden walls
• Start layout/digging bio-retention pond

Existing Building Renovations
• Tape and finish walls and ceilings
• MEP rough-in hard ceilings
• MEP rough-in acoustical ceilings

Storage Bar
• Framing interior walls
• Hang interior walls
• Continue exterior brick façade

Next week - Activities/Issues:
New Gallery / Connector
• Complete curtain wall glass
• Continue framing walls and soffits
• Complete connector roof
• Start MEP wall rough-in

Existing Building Renovations
• Tape & finish walls and ceilings
• Start priming interior walls

Storage Bar
• Complete exterior CMU and brick walls.
• Finish MEP overhead rough-in.
• Continue framing interior walls

Storage bar exterior

Sculpture garden progress

Sculpture garden curtain wall

No comments: