Current week - Activities/Issues:
New Gallery / Connector
• Framing connector walls/soffit
• Completed MEP overhead trim out
• Installing glass at the connector curtainwall
• Backfill sculpture garden walls
• Start layout/digging bio-retention pond
Existing Building Renovations
• Tape and finish walls and ceilings
• MEP rough-in hard ceilings
• MEP rough-in acoustical ceilings
Storage Bar
• Framing and hanging interior walls
• Completed exterior brick façade
Next week - Activities/Issues:
New Gallery / Connector
• Complete curtain wall glass
• Continue framing walls and soffits
• Turn HVAC units on in gallery
• Build scaffold in connector
• Hanging walls in connector
• Installing sewer line at east entry
• Demo existing brick wall at east entry
Existing Building Renovations
• Tape & finish walls and ceilings
• Start priming interior walls
Storage Bar
• Finish MEP overhead rough-in.
• Continue Framing interior walls
• Installing windows
• Back filling storage bar
And here are the associated images:
East entry progress
Sculpture garden progress
Sculpture garden curtain wall
Now, here's the report for the week that just ended, the week of March 26, 2010:
Current week - Activities/Issues:
New Gallery / Connector
· Complete curtain wall at connector
· Complete framing walls and soffits at connector
· Start hanging walls in connector
· Turn on HVAC units in gallery
Existing Building Renovations
· Install sanitary sewer line at east entry
· Start brick demo at east entry
· Tape and finish walls and ceilings
· Start priming interior walls
Storage Bar
· Finish MEP overhead rough-in
· Install windows
· Framing interior walls
· Backfill storage bar
Next week - Activities/Issues:
New Gallery / Connector
· MEP rough-in soffits at connector
· Hang walls in connector
· Hang ceilings in connector
· Prime walls/ceilings in gallery
Existing Building Renovations
· Complete brick demo at new east entry
· Start concrete footings at new east entry
· Continue priming interior walls
Storage Bar
· Finish MEP overhead rough-in
· Install 3rd floor ceiling grid
· Frame 2nd floor interior walls
And here are its pictures:
Storage bar exterior
Gallery parking ceiling framing
Gallery interior progress
No comments: