Current week - Activities/Issues:
New Gallery / Connector
• Skylights have been installed.
• North and West exterior wall vapor barrier is complete.
• Gallery TPO roof membrane is complete.
• Continued to install exterior limestone façade.
• Completed CMU masonry on the 1st floor.
• Started MEP overhead on 1st floor.
• Started connector SOG waterproofing.
• Completed spray fireproofing in the gallery.
• Continued the connector roofing.
Storage Bar
• Completed erecting structural steel.
• Completed installing metal decking.
• Completed structural tie-ins to the existing building.
Next week - Activities/Issues:
New Gallery / Connector
• Continue working on connector roofing.
• Continue to install the exterior vapor barrier and limestone.
• Continue MEP overhead in the gallery.
• Continue to prep for the connector SOG and elevated deck.
• Start layout for connector curtain wall.
• Damp proof the 1st floor CMU.
• Start metal panels on skylights
• Reworking brick on connector
Existing Building Renovations
• Continue with the MEP overhead rough-in.
Storage Bar
• Start the exterior concrete wall waterproofing / vapor barrier.
• Fine grade SOG.
• Start Exterior CMU
Limestone on new gallery
Storage bar structure
Connector slab prep
2nd-floor ceiling ductwork