Current week - Activities/Issues:
New Gallery / Connector
• Completed skylight metal panels
• Completed Gallery Vapor Barrier
• Completed West elevation limestone
• Installing 1st Floor Brick
• Continue MEP overhead 1st Floor
• Continue MEP overhead 2nd Floor
• Gallery Spray Insulation is complete
• Gallery interior wall vapor barrier started
Storage Bar
• Completing structural tie ins to existing building
• Continue the exterior concrete wall waterproofing / vapor barrier.
Next week - Activities/Issues:
New Gallery / Connector
• Continue working on connector roofing.
• Continue to install the exterior vapor barrier and limestone.
• Continue MEP overhead in the gallery.
• Complete water test of skylights
• Installing interior vapor barrier gallery.
Existing Building Renovations
• Continue with the MEP overhead rough-in.
• Start framing walls
Storage Bar
• Pour elevated slabs
• Start Exterior wall framing
• Pour S.O.G.

Gallery window glass

3rd-floor interior wall framing

1st-floor connector poured concrete