Current week - Activities/Issues:
New Gallery / Connector
• Completes framing walls; soffits ongoing
• Turn on HVAC units in gallery
• MEP trim out gallery ceiling
• Framing hard ceiling connector
• Interior brick in connector
Existing Building Renovations
• Install sanitary sewer line at east entry
• Continue brick demo at east entry
• Tape and finish walls and ceilings
• Continue priming interior walls
Storage Bar
• Completed MEP overhead rough-in
• Framing interior walls
• Backfill storage bar
Next week - Activities/Issues:
New Gallery / Connector
• MEP rough-in soffits at connector
• Hang ceilings in connector
• Prime walls/ceilings in gallery
Existing Building Renovations
• Complete brick demo at new east entry
• Start east entry structure steel
• Continue priming interior walls
• Install storage bar exterior stair
Storage Bar
• Finish MEP overhead rough-in
• Install 3rd floor ceiling grid and complete demo of all floors
• Frame 2nd floor interior walls

Sculpture garden/connector/installation of new third-floor windows

Connector brick column

Café interior renovation and demolition