Current week - Activities/Issues:
New Gallery / Connector
· Wood floor sleeper system started
· Started terrazzo in connector
· Started restroom tile
Existing Building Renovations
· Continue painting existing walls
· Completed repairs to existing brick
Storage Bar
· Completed low roof installation
Site / Sculpture Garden
· Poured final wall section
· Installed water vault
· Installing irrigation system
Next week - Activities/Issues:
New Gallery / Connector
· Continue wood floor
Existing Building Renovations
· Start below SOG vapor barrier at the east alternate entry
· Start roofing / gutters for the east alternate entry
· Continue to finish walls and prime paint
· Begin 3rd floor millwork
Storage Bar
· Begin 3rd floor millwork
· Hang drywall in the 2nd floor
Site / Sculpture Garden
· Continue to excavate cistern tank and water pump tank
· Pour concrete pavers
· Spread topsoil

Restroom terrazzo floor tile

Restroom ceramic tile

Connector terrazzo mud bed