Current week - Activities/Issues:
New Gallery / Connector
• Wood floor sleeper system has started
• Started terrazzo in the connector
• Setting restroom tile and fixtures
Existing Building Renovations
• Continue painting existing walls
• Carpet and millwork started in existing building
• Hanging doors and hardware
Storage Bar
• Completed hanging drywall on 2nd floor
• Repairing fire proofing on 2nd floor
Site / Sculpture Garden
• Poured final wall section
• Installing irrigation system / electrical rough in below grade
• Installing topsoil
Next week - Activities/Issues:
New Gallery / Connector
• Continue wood floor installation
Existing Building Renovations
• Start roofing / gutters for the east alternate entry
• Continue to finish and prime paint on walls
• Continue to install millwork and finishes
Storage Bar
• Hang and finish drywall in the 2nd floor
Site / Sculpture Garden
• Continue to excavate cistern tank and water pump tank
• Pour concrete pavers
• Spread topsoil
Connector terrazzo tile installation
3rd-floor carpet installation
1st-floor café-area renovation progress
No comments:
Post a Comment