Friday, May 07, 2010

Construction Updates from Holder

Here's the update from Holder for the week ending today (Friday, May 7, 2010):

Current week - Activities/Issues:
New Gallery / Connector
• Wood floor sleeper system has started
• Started terrazzo in the connector
• Setting restroom tile and fixtures

Existing Building Renovations
• Continue painting existing walls
• Carpet and millwork started in existing building
• Hanging doors and hardware

Storage Bar
• Completed hanging drywall on 2nd floor
• Repairing fire proofing on 2nd floor

Site / Sculpture Garden
• Poured final wall section
• Installing irrigation system / electrical rough in below grade
• Installing topsoil

Next week - Activities/Issues:
New Gallery / Connector
• Continue wood floor installation

Existing Building Renovations
• Start roofing / gutters for the east alternate entry
• Continue to finish and prime paint on walls
• Continue to install millwork and finishes

Storage Bar
• Hang and finish drywall in the 2nd floor

Site / Sculpture Garden
• Continue to excavate cistern tank and water pump tank
• Pour concrete pavers
• Spread topsoil

Connector terrazzo tile installation

3rd-floor carpet installation

1st-floor café-area renovation progress

No comments: