Here are the construction updates from the week of July 30th.
Current week - Activities/Issues:
New Gallery / Connector
• Installing intumescent paint
• Final finish on wood floors
• Installing Skylight shades
Existing Building Renovations
• Walking off Completion List
Storage Bar
• Walking off Completion List
Site / Sculpture Garden
• Installed BRAE cistern pump system
• Planted trees
• Striping/wheel stops in parking area
Next week - Activities/Issues:
New Gallery / Connector
• Final clean
• Signage
Existing Building Renovations
• Final cleaning
• Walk off completion list
• Install aluminum awning/metal panels
Storage Bar
• Walk off Completion list
Site / Sculpture Garden
• Walk off Completion list
Lights installed in parking garage area