Tuesday, August 17, 2010

Construction Updates from Holder

Here are the construction updates from the week of August 13.

Current week - Activities/Issues:

• Installing Skylight shades

• Installing interior/exterior signage

• Painting AESS Exposed Steel

• Working on punchlist items

• Working on miscellaneous millwork items

• Sealing concrete floors

• Functional testing of building systems


Next week - Activities/Issues:

• Sealing concrete floors

• Terrazzo tile repairs

• Work on punchlist

• Continue installation of interior signage

• Finish window blinds

• Complete misc. millwork items

• Design team punch galleries, connector and lobby



Interior Lobby GMOA Logo

Interior Gallery Signage

Connector Glass Railings & Tile