Current week - Activities/Issues:
• Installing Skylight shades
• Installing interior/exterior signage
• Completed painting AESS Exposed Steel
• Working on punch list items
• Working on miscellaneous millwork items
• Sealing concrete floors
• Functional testing of building systems
Next week - Activities/Issues:
• Start demolition and build out of café
• Terrazzo tile repairs
• Work on punch list throughout the building
• Continue installation of interior signage
• Finish window blinds
• Complete misc. millwork items
• Design team punch galleries, connector and lobby

South elevation exterior with landscaping

Gallery display cabinets

Exterior lights on site wall

Exterior concrete benches