Tuesday, September 15, 2009

Construction Updates from Holder

Here's the construction update from September 11, 2009:

Current week - Activities/Issues:
New Gallery / Connector
• Finished roof joists.
• Finished roof decking.
• Installed skylight structural steel support.
• Poured concrete columns at the parking area.
• Finished the retaining wall footings.
• Completed the Limestone mock-up.
• Formed the signage wall.

Existing Building Renovations
• Started to relocate emergency power through building.

Storage Bar
• Continued to address and relocate existing site utilities including:
o Emergency Power
o Domestic Water

Next week - Activities/Issues:

New Gallery / Connector
• Pour the balance of the concrete columns.
• Form and pour the signage wall.
• Start below grade waterproofing.
• Start below grade masonry walls.

Existing Building Renovations
• Complete the relocation of emergency power.
• Complete the existing utility investigation.

Storage Bar
• Continue to relocate existing utilities.
• Finish mass excavation.
• Dig footings.


Skylight support framing



Signage wall formwork/resteel



Elevated slab with Nelson studs, wire mesh, and rebar

No comments: