Sept. 18, 2009
Current week - Activities/Issues:
New Gallery / Connector
• Completed the skylight structural steel support.
• Poured balance of concrete columns.
• Poured 1st half of the signage wall.
• Started below grade waterproofing.
• Started the 1st floor masonry walls.
• Prepared for elevated slab pours.
Existing Building Renovations
• Complete the emergency power relocates.
Storage Bar
• Started to mass excavate under new structure.
• Relocated the existing domestic water.
Next week - Activities/Issues:
New Gallery / Connector
• Pour the 2nd half of the signage wall.
• Pour the West end of the elevated gallery slab.
• Pour the East end of the elevated gallery slab.
• Start removing the existing brick façade at the connector.
Existing Building Renovations
• Finish the balance of the interior demolition.
Storage Bar
• Complete mass excavation.
• Start digging footings.
Structure view from Carlton Street
1st half of signage wall poured
1st-floor masonry
No comments:
Post a Comment