Current week - Activities/Issues:
New Gallery / Connector
• Poured the signage wall.
• Poured the elevated gallery slab.
• Started the 1st floor below grade plumbing.
• Removed the existing brick walls at the connector.
• Started to install the brick relief outriggers.
Existing Building Renovations
• Started the ceiling/overhead demo in the Kennedy/Alston gallery.
• Completed as-built surveys of the existing security/alarm systems.
• Set-up the trending and testing equipment to monitor the existing systems.
Storage Bar
• Started to install the final below grade CW configuration.
• Completed the domestic water relocation.
Next week - Activities/Issues:
New Gallery / Connector
• Start to frame the exterior gallery walls.
• Continue to form and pour the site retaining walls.
• Start the erection of the connector structural steel.
• Finish the gallery outriggers, tube steel and brick relief angle.
Existing Building Renovations
• Continue to demo the existing building systems.
Storage Bar
• Start footing excavation.
• Form foundations.
Signage wall complete
Gallery elevated slab poured
1st-floor plumbing rough-in
No comments:
Post a Comment