Tuesday, September 29, 2009

Construction Updates from Holder

Here's Holder's construction update from the week of Sept. 25. Amazingly, despite the torrential rains last week, we have only lost one day due to rain.

Current week - Activities/Issues:
New Gallery / Connector
• Poured the signage wall.
• Poured the elevated gallery slab.
• Started the 1st floor below grade plumbing.
• Removed the existing brick walls at the connector.
• Started to install the brick relief outriggers.

Existing Building Renovations
• Started the ceiling/overhead demo in the Kennedy/Alston gallery.
• Completed as-built surveys of the existing security/alarm systems.
• Set-up the trending and testing equipment to monitor the existing systems.

Storage Bar
• Started to install the final below grade CW configuration.
• Completed the domestic water relocation.

Next week - Activities/Issues:
New Gallery / Connector
• Start to frame the exterior gallery walls.
• Continue to form and pour the site retaining walls.
• Start the erection of the connector structural steel.
• Finish the gallery outriggers, tube steel and brick relief angle.

Existing Building Renovations
• Continue to demo the existing building systems.

Storage Bar
• Start footing excavation.
• Form foundations.


Signage wall complete


Gallery elevated slab poured


1st-floor plumbing rough-in

No comments: