Current week - Activities/Issues:
New Gallery / Connector
• Started the connector structural steel erection.
• Started roof parapet framing.
• Started skylight framing.
• Completed exterior stud framing.
• Started below SOG water proofing.
• Installed outriggers, tube steel and brick relief miscellaneous steel.
Existing Building Renovations
• Continued with the CW piping installation inside the 1st floor mechanical room.
Storage Bar
• Installed the new 4” CW lines to the storage bar.
Next week - Activities/Issues:
New Gallery / Connector
• Continue framing the roof parapet and sky lights.
• Continue to form and pour the site retaining walls.
• Finish the gallery outriggers, tube steel and brick relief angle.
• Continuing erecting the connector structural steel.
• Pour gallery SOG.
Existing Building Renovations
• Continue to demo / relocating the existing building systems.
Storage Bar
• Completed the underground C.W. piping

Looking up at the southeast corner of the galleries

Framing the skylight walls

Structural steel for the connector
No comments:
Post a Comment