Current week - Activities/Issues:
New Gallery / Connector
• Continue framing the roof parapet and sky lights.
• Continue to form and pour the site retaining walls.
• Finish the gallery outriggers, tube steel and brick relief angle.
• Continuing erecting the connector structural steel.
• Continued to prep for SOG pour.
• Improved the site erosion control.
Existing Building Renovations
• Continued with the CW piping installation inside the 1st floor mechanical room.
Storage Bar
• Continued to install the new 4” CW lines to the storage bar.
Next week - Activities/Issues:
New Gallery / Connector
• Install 2’ band of roofing sheathing and vapor barrier at skylight.
• Continue framing the roof parapet and sky lights.
• Continue to form and pour the site retaining walls.
• Continuing erecting the connector structural steel.
• Continue gallery SOG preparation.
Existing Building Renovations
• Continue to demo / relocating the existing building systems.
Storage Bar
• Completed the underground C.W. piping

Slab on grade prep

Skylight framing

Sculpture garden

Exterior stud framing
No comments:
Post a Comment