Here are the updates from Holder for the past two weeks.
Week ending on 5/21:
New Gallery/Connector
- Installing wood flooring in gallery
- Installing terrazzo flooring in connector
- Final water test for skylights
Existing Building Renovations
- Continue to finish painting existing walls
- Installing millwork/shelving
- Complete east entry revisions
Storage Bar
- Repaired spray fire proofing
- Coated the fireproofing
- MEP trim out
Site/Sculpture Garden
- Poured stairs, ramps and walk pads
- Excavating cistern
Week ending on 5/28:
New Gallery/Connector
- Sanding and finishing wood flooring in gallery
- Installing floor expansion joint in connector
- Finishing terazzo base and grout
Existing Building Renovations
- Continue to finish painting existing walls
- Installing millwork/shelving
- MEP final trim out
- Installing doors and hardware
Storage Bar
- Completed the repairing of spray fire proofing
- Continue MEP trim out
Site/Sculpture Garden
- Poured stairs, ramps and walk pads and continued installing planting beds
- Completed excavating of cistern
Next week - Activities/Issues
New Gallery/Connector
- Installing handrails on connector stairs
- Start painting structural steel
- Finish terrazzo
Existing Building Renovations
- Fireproof structural steel on east entry
- Continue interior wall framing of east entry
Storage Bar
- Finish painting of storage areas
Site/Sculpture Garden
- Set cistern tank and piping
- Plant trees
Terrazzo installation in lobby
Gallery wood flooring
Sculpture garden walk paths
Check out the construction webcam here and keep reading the blog for updates!