Construction updates from Holder

Here are the construction updates from Holder for the week of June 4.

Current week - Activities/Issues:

New Gallery/Connector
  • Installing stainless rails in connector
  • Installing protection on wood floor
  • Finishing terrazzo base and grout
Existing Building Renovations
  • Continue to finish painting existing walls
  • Installing millwork/shelving
  • MEP final trim out
  • Installing doors and hardware
Storage Bar
  • Installing punch window opening on third floor
  • Continue MEP trim out
Site/Sculpture Garden
  • Poured stairs, ramps and walk pads and continued installing plant beds
  • Setting cistern tanks
Next week - Activities/Issues:

New Gallery/Connector
  • Complete removable walls
  • Complete stair handrails
  • Installing millwork
Existing Building Renovations
  • Continue HCC Completion List
Storage Bar
  • Complete drywall
  • Finish windows
Site/Sculpture Garden
  • Back filling cistern
  • Digging bioretention pond

Sculpture garden landscaping

East entry interior progress

Cistern installation