Here are the construction updates from Holder for the week of June 4.
Current week - Activities/Issues:
New Gallery/Connector
- Installing stainless rails in connector
- Installing protection on wood floor
- Finishing terrazzo base and grout
Existing Building Renovations
- Continue to finish painting existing walls
- Installing millwork/shelving
- MEP final trim out
- Installing doors and hardware
Storage Bar
- Installing punch window opening on third floor
- Continue MEP trim out
Site/Sculpture Garden
- Poured stairs, ramps and walk pads and continued installing plant beds
- Setting cistern tanks
Next week - Activities/Issues:
New Gallery/Connector
- Complete removable walls
- Complete stair handrails
- Installing millwork
Existing Building Renovations
- Continue HCC Completion List
Storage Bar
- Complete drywall
- Finish windows
Site/Sculpture Garden
- Back filling cistern
- Digging bioretention pond

Sculpture garden landscaping

East entry interior progress

Cistern installation