Here are the construction updates from the week of June 18.
Current week - Activities/Issues:
New Gallery/Connector
- Building removable walls
- Bondo monumental stairs
- Started monumental stair treads
Existing Building Renovations
- Installing first floor lobby ceiling
- Refinish gallery 251 wood floor
- MEP final trim out
- Install linoleum in catering kitchen
Storage Bar
- Installing punch window opening on third floor
- Completed MEP trim out
Site/Sculpture Garden
- Placed granite treads
- Backfilling cistern tanks
- Start trellis installation
Next week - Activities/Issues:
New Gallery/Connector
- Complete removable walls
- Complete stair handrails
Existing Building Renovations
- Complete installation of catering kitchen millwork
- Finishes in first floor lobby
Storage Bar
- Final paint
Site/Sculpture Garden
- Continue stainless steel fencing
- Continue to install plants

Removable walls construction

Driveway asphalt progress

Catering kitchen millwork installation
No comments:
Post a Comment