Wednesday, June 16, 2010

Construction Updates from Holder

Here are the construction updates from Holder through Friday, June 11.

Current week - Activities/Issues:


New Gallery / Connector

• Building removable walls

• Installing wood bases

• Trim out of light fixtures


Existing Building Renovations

• Installing 1st floor lobby ceiling

• Installing millwork / shelving

• MEP final trim out

• Installing doors and hardware


Storage Bar

• Installing punch window opening on third floor

• Continue MEP trim out


Site / Sculpture Garden

• Poured stairs, ramps, and walk pads and continued installing planting beds

• Backfilling cistern tanks



Next week - Activities/Issues:


New Gallery / Connector

• Complete removable walls

• Complete stair handrails

• Installing millwork


Existing Building Renovations

• Continue HCC Completion List

• Finishes in 1st floor lobby


Storage Bar

• Final paint


Site / Sculpture Garden


• Back filling cistern/piping

• Continue to install plants

Parking Garage Roof Installation Progress

Removable Walls Construction

Landing and Stairwell Railing Installation