Current week - Activities/Issues:
New Gallery / Connector
• Building removable walls
• Installing wood bases
• Trim out of light fixtures
Existing Building Renovations
• Installing 1st floor lobby ceiling
• Installing millwork / shelving
• MEP final trim out
• Installing doors and hardware
Storage Bar
• Installing punch window opening on third floor
• Continue MEP trim out
Site / Sculpture Garden
• Poured stairs, ramps, and walk pads and continued installing planting beds
• Backfilling cistern tanks
Next week - Activities/Issues:
New Gallery / Connector
• Complete removable walls
• Complete stair handrails
• Installing millwork
Existing Building Renovations
• Continue HCC Completion List
• Finishes in 1st floor lobby
Storage Bar
• Final paint
Site / Sculpture Garden
• Back filling cistern/piping
• Continue to install plants



Landing and Stairwell Railing Installation
No comments:
Post a Comment