Here are the construction updates from the week of June 25.
Current week - Activities/Issues:
New Gallery/Connector
- Removable walls complete
- Reworking doors
- Install glass and stainless steel handrails
Existing Building Renovations
- Installing first floor lobby ceiling
- Re-finish gallery 251 wood floor
- Install linoleum in catering kitchen
Storage Bar
- Installing punch window opening on third floor
- Completed MEP trim out
- Start punch list
Site/Sculpture Garden
- Finish grading of cistern
- Working on installing sidewalks
- Start trellis installation
Next week - Activities/Issues:
New Gallery/Connector
- Complete grouting of floors
- Complete stair handrails
Existing Building Renovations
- Complete installation of catering kitchen millwork
- Finishes in first floor lobby
Storage Bar
- Final paint
Site/Sculpture Garden
- Continue stainless steel fencing
- Continue to install plants
Ceiling installation in parking garage
Sculpture garden water feature
Glass installation on stair railings